I have a running schedule with mutlile tasks scheduled for different day # or
the same and would like to have the dates auto fill in once I enter the start
date.
example:
4/20/06 task 1 day 1
? task 2 day 2
? task 3 day 2
? task 4 day 3

Keeping in mind that I don't want to include weekends and that I'll need to
delete a range of holiday dates.

Please help. Thank you

See reply in .Functions

Biff

quot;JPquot; gt; wrote in message
...
gt;I have a running schedule with mutlile tasks scheduled for different day #
gt;or
gt; the same and would like to have the dates auto fill in once I enter the
gt; start
gt; date.
gt; example:
gt; 4/20/06 task 1 day 1
gt; ? task 2 day 2
gt; ? task 3 day 2
gt; ? task 4 day 3
gt;
gt; Keeping in mind that I don't want to include weekends and that I'll need
gt; to
gt; delete a range of holiday dates.
gt;
gt; Please help. Thank you